The installation of the inner and outer parts of the steel structures of the 215-tonne passive heat removal system was completed in two days on Rooppur 2 in Bangladesh, Rosatom says.

The process involves the installation - with a maximum allowable deviation of 1 centimetre - of the two parts 64.5 metres high, bringing the reactor building's height to a total of 74.85 metres.


The passive heat removal system (PHRS) is a safety feature which, in the event of a loss of on-site power supply, provides long-term heat removal from the reactor core to the atmosphere using natural circulation - outside air comes into heat exchangers, is heated up, then rises through air ducts to the outlet header located on top of the dome, and returns to the atmosphere, thus cooling down the reactor compartment.

The Rooppur plant, 160 kilometres from the capital Dhaka, will feature two Russian VVER-1200 reactors. Construction of the first unit began in November 2017 and it is scheduled to be commissioned in 2024. Construction of the second unit began in July 2018. They have an initial life-cycle of 60 years, with a further 20-year extension possible.

Bangladesh officially became a member of the international 'club' of nuclear countries in October when the first fuel for the plant was delivered to the Rooppur site. The project follows a February 2011 agreement with Rosatom for two reactors to be built at Rooppur for the Bangladesh Atomic Energy Commission. The initial contract for the project, worth USD12.65 billion, was signed in December 2015.

Alexey Deriy, ASE JSC vice president and director of the Rooppur NPP construction project, said: "Installing two parts of the PHRS deflector in the design position in two days is a record." He said the next stage was to install the service platforms and air ducts.

Kaynak:https://www.world-nuclear-news.org/Articles/In-pictures-Rooppur-2-passive-heat-removal-system

Diğer Haberler

2
Nisan 2022
Nükleer Güvenlik için Önemli İş Birliği

Nükleer güvenlik için önemli işbirliği Rusya ve Ukrayna savaşının nükleer bir felakete yol açmaması için Ukrayna'ya giden Uluslararası Nükleer Enerji Ajansı Genel Müdürü Rafael Mariano Grossi, Rusya'ya geçti.

1
Temmuz 2022
İlk Nükleer Santral için Anlaştılar

Fransız enerji sağlayıcısı EDF, Polonya'da ilk nükleer santralin kurulmasına ilişkin ülkedeki 5 firma ile işbirliği anlaşması imzaladı.

20
Şubat 2023
Çin Nükleer Isıtma Ağını Genişletiyor

Çin’in Shandong Eyaleti’nde nükleer enerji ile üretilen ısıyı şehirlere taşıyacak ilk uzun mesafeli boru hattı inşaatına başlandı. Hat ile 1 milyon kişinin ısınması sağlanacak.

20
Şubat 2023
University of Michigan Working Toward Next Phase of Nuclear Energy

Much smaller nuclear power plants could prove to be the next phase of nuclear energy in the U.S.

21
Şubat 2023
First Nuclear Plant of North India to be Built in Haryana

First nuclear plant of North India in Haryana: The first nuclear power plant in North India would be built in Gorakhpur, Haryana, according to Union Minister Jitendra Singh.